Overview

Hotel Building Near Powai

Problem:

  • Additional load of kitchen equipment called for strengthening of beams
  • Separation crack was observed at end of lift shaft and shear wall

Solution :

  • Beams were analyzed for additional load.
  • A glass fiber wrapping system was designed and applied to tackle the additional load on beams.
  • Crack were opened up and sealed with epoxy inner cavity was grouted with epoxy grouts.
  • System of prestressed and non-prestressed carbon fiber laminates and fiber wraps was applied on shear-wall.

Overview

Taj Connemara, Chennai

Problem :

  • Over a considerable period of time corrosion and carbonation had affected the RCC columns of a hotel building in the coastal area of Chennai
  • NDT reports indicated performance level in mid and lower range

Solution:

  • Consultant had suggested for steel treatment and Section built-up using PMM
  • Columns were wrapped with single layer of glass fiber wrap improving durability and strength.
  • Work was carried out giving due attention to safety and cleanliness.

Overview

Otters Club in Bandra

Problem:

  • More than 50 years old structure in CRZ zone.
  • Impractical to demolish and reconstruct so a major restoration work was executed.
  • Exposure to marine environment damages to RCC and plinth were mainly observed.

Solution:

  • Soil stabilization and strengthening of plinth beam with conventional structural steel.
  • Structural elements were treated for corrosion damages, damaged RCC sections were re-cast.
  • Conventional waterproofing for terrace slab.
  • Microstructure of concrete was improved using epoxy grouting and durability aspect was taken care with corrosion inhibitors and further wrapped using GFRP wraps.
  • Sanrachana was entrusted the responsibility and delivered successfully in line with client’s expectations

Overview

Oberoi Hotel, New Delhi

Problem :
  • Hotel building showed corrosion damages due to environmental exposure over a period of time
Solution :
  • Steel Treatment for corrosion protection
  • Application of corrosion inhibitors
  • Damaged concrete section was rebuilt using polymer modified mortar and concrete.
  • Work was carried in adherence to strict shutdown timelines