Additional load of kitchen equipment called for strengthening of beams
Separation crack was observed at end of lift shaft and shear wall
Solution :
Beams were analyzed for additional load.
A glass fiber wrapping system was designed and applied to tackle the additional load on beams.
Crack were opened up and sealed with epoxy inner cavity was grouted with epoxy grouts.
System of prestressed and non-prestressed carbon fiber laminates and fiber wraps was applied on shear-wall.
Overview
Taj Connemara, Chennai
Problem :
Over a considerable period of time corrosion and carbonation had affected the RCC columns of a hotel building in the coastal area of Chennai
NDT reports indicated performance level in mid and lower range
Solution:
Consultant had suggested for steel treatment and Section built-up using PMM
Columns were wrapped with single layer of glass fiber wrap improving durability and strength.
Work was carried out giving due attention to safety and cleanliness.
Overview
Otters Club in Bandra
Problem:
More than 50 years old structure in CRZ zone.
Impractical to demolish and reconstruct so a major restoration work was executed.
Exposure to marine environment damages to RCC and plinth were mainly observed.
Solution:
Soil stabilization and strengthening of plinth beam with conventional structural steel.
Structural elements were treated for corrosion damages, damaged RCC sections were re-cast.
Conventional waterproofing for terrace slab.
Microstructure of concrete was improved using epoxy grouting and durability aspect was taken care with corrosion inhibitors and further wrapped using GFRP wraps.
Sanrachana was entrusted the responsibility and delivered successfully in line with client’s expectations
Overview
Oberoi Hotel, New Delhi
Problem :
Hotel building showed corrosion damages due to environmental exposure over a period of time
Solution :
Steel Treatment for corrosion protection
Application of corrosion inhibitors
Damaged concrete section was rebuilt using polymer modified mortar and concrete.
Work was carried in adherence to strict shutdown timelines